Programme
DAY 1
Review of concrete properties
- Strength grades
- The trouble with water/cement ratio
- Consistence
- Cohesion, segregation and bleeding
- Durability
Materials update
- Cementitious materials
- Properties of blended cements
- Aggregates including “fines”
- Admixtures, Additives and Additions
Concrete faults (1)
- Construction defects
- Blow holes
- Honeycombing
- Grout loss
- Scour
- Water runs & sand streaks
Laboratory practical exercise:
- Trial mixes
- Effect of changing the water/cement ratio
- Slump testing
- Flowing/self-compacting concrete
- Air content
- Cube making and curing
- Demonstration – Cube testing
Concrete faults (2)
- Non-structural cracking
- Thermal cracking
- Plastic cracking
- Plastic settlement
- Plastic shrinkage
- Drying Shrinkage
Overnight syndicate project:
- Early-age cracking.
DAY 2
Syndicate reports
Outline of concrete types
- Nominal mixes
- Prescribed concretes
- Standardized prescribed concretes
- Designed concretes
- Designated concretes
- Proprietary concretes
- Durability criteria
Concretes for specific applications
- Selecting appropriate workability levels
- Watertight construction
- High quality surface finishes
Supervision of concrete construction (1)
- Procurement of concrete
- Checking and testing
- What to do if the slump is wrong
- Transporting concrete
Supervision of concrete construction (2)
- Compaction
- Over-vibration
- Under-vibration
- Secondary vibration
- Curing
Conformity criteria (1)
- Interpretation of test results
Evaluating test results
- Comparing yesterday’s trial mixes
Conformity criteria (2)
- Action on non-conformity
Contractor-specific topics
Questions, answers and final discussion.
Duration: 2 Days
Cost: £575 + VAT